Preventive maintenance

Preventive maintenance: types, real examples and how to start in one week

Preventive maintenance is planned work you do on a machine before it fails: cleaning, lubrication, inspection, adjustment and replacing parts that wear, on a schedule set by time, usage or condition. You spend a little planned time to lose less unplanned time. You can start in one week with your most critical machines, a short checklist for each, and one person who owns the schedule.

By Jay Sampat, Co-founder, Codiot TechnologiesPublished Last reviewed 7 min read

Why preventive maintenance works A pencil sketch of machine condition over time. Without maintenance, a grey line wears steadily down until it crosses the failure line and the machine breaks down. With preventive maintenance, an orange line wears down a little, then each planned PM brings it back up, so it never reaches the failure line. MACHINE CONDITION TIME PMPMPMPM Failure line Breakdown without PM With PM: small, planned resets
Without PM, condition wears down until the machine breaks. With PM, small planned jobs reset the wear before it reaches the failure line.

What is preventive maintenance?

Preventive maintenance (PM) is maintenance you plan and carry out before a failure, to keep a machine able to do its job. The work is usually small: clean, lubricate, inspect, tighten, adjust, and replace parts that wear on a known pattern, such as filters, belts, hoses and seals.

It is different from breakdown maintenance, where you repair after the machine stops, and from corrective work raised when an inspection finds a defect. A working PM programme turns some of tomorrow's breakdowns into today's short jobs, done in a planned stop instead of in the middle of an order.

PM is not the right answer for every asset. A cheap, non-critical item with a spare on the shelf, such as a pedestal fan, can run to failure by choice. The point is to decide machine by machine, so the default is no longer "fix it when it breaks".

In plants that follow total productive maintenance (TPM), operators take on the simplest PM tasks, such as daily cleaning, lubrication and visual checks, and the maintenance team handles the rest. See our guide to total productive maintenance for how that split works.

The four types, and when to use each

Most plants use a mix. Pick the trigger that matches how the machine actually wears, not the one that is easiest to put in a spreadsheet.

Types of preventive maintenance by trigger
TypeWhat triggers the workExampleGood fit for
Time-basedA calendar interval: daily, weekly, monthly, yearlyMonthly cleaning of the filters on a control panelAssets that wear steadily, and statutory or safety checks
Usage-basedRun hours, cycles, strokes or output since the last PMCompressor oil and filter change after a set number of running hoursMachines whose load changes with the production plan
Condition-basedA reading crosses a limit: vibration, temperature, pressureBearing inspection when pump vibration passes its warning limitCritical rotating equipment where a reading shows wear early
PredictiveA trend in condition readings shows when a limit will be crossedPlanning a motor bearing change for the next planned stop from a rising temperature trendHigh-value assets with reliable readings

A useful fifth option is "whichever comes first": the PM falls due on a date or at a usage interval, whichever is reached first. It suits machines that sit idle for weeks and then run hard.

Real examples from common plant machines

Copy this as a starting checklist. The intervals are typical starting points, not rules: your OEM manual, your operating hours and your own breakdown history decide the final interval.

Starter PM tasks for common machines
MachinePM taskTriggerStarting interval
Screw air compressorCheck oil level, drain condensate, clean the intake filterTimeDaily check, weekly filter clean
Screw air compressorChange oil, oil filter and air filter elementUsageOEM running-hour interval
Hydraulic pressCheck oil level and temperature, look for leaks at hoses and fittingsTimeEvery shift
Hydraulic pressReplace the return-line filter, take an oil sampleWhichever comes firstOEM hours or six months
CNC machining centreClean the chip conveyor and coolant tank, check way lube levelTimeDaily and weekly
CNC machining centreRecord spindle temperature and vibration against a baselineConditionMonthly reading
Centrifugal pumpCheck the seal for leaks, bearing temperature and vibrationConditionWeekly round
Belt conveyorCheck belt tension, tracking and idlers, grease the bearingsTimeWeekly
EOT crane or hoistInspect wire rope, hook, brake and limit switchesTimeMonthly in-house check, plus the statutory examination your factory rules require

Every task needs three things written down: what to check, the acceptable limit, and what to do when the reading is outside it.

How to start in one week

You do not need software, a consultant or a full asset register to begin. You need one owner, a short list of machines and the discipline to record what you find. Here is a plan that fits in one working week.

  1. Day 1: list and rank. Walk the floor and list your machines. Mark the ones that stop the line, are hard to repair or have no standby. Pick about ten.
  2. Day 2: gather what you know. Collect the OEM manuals and the last year of breakdowns for those machines, from registers, WhatsApp messages and the shift log. Note what failed and how often.
  3. Day 3: write short checklists. For each critical machine, write five to ten tasks from the manual and the failure history. Plain words, one check per line, with the limit.
  4. Day 4: set triggers. Give each task a trigger and an interval: calendar, run hours, or whichever comes first. Where you have no data, start with the OEM interval.
  5. Day 5: assign owners and slots. Name who does each task, operator or technician. Agree with production when the planned stop is, so PMs do not compete with orders.
  6. Day 6: run the first PMs. Do the first round, record readings and photos, and raise a work order for every defect found.
  7. Day 7: review. Count what was done, what was missed and why, and what the PMs found. Fix the checklists that were unclear.
A preventive maintenance start in seven days A seven-day checklist ticks itself, one day at a time: list machines and pick the critical ones; gather manuals and breakdown history; write short checklists; set triggers and intervals; assign owners and planned stop slots; run the first PMs; review what was done and found. DAY 1List machines, pick the critical ones DAY 2Gather manuals and breakdown history DAY 3Write a short checklist per machine DAY 4Set a trigger and interval per task DAY 5Assign owners and planned stop slots DAY 6Run the first PMs, record readings DAY 7Review what was done, missed, found
The seven-day start, one step per day.

After the first week, keep the same ten machines for a month before you add more. A small plan that runs every week beats a large plan that runs once.

A worked example from a typical Indian plant

Worked example (illustrative)

Take a forging and machining plant near Pune with about 140 assets. In week one the team picks 12 critical machines: two compressors, four hydraulic presses, four CNCs, a cooling-water pump and an EOT crane. They write 38 PM tasks across those machines. All numbers below are illustrative.

PM compliance is the share of PMs done within their window: PMs done on time divided by PMs due in the period, times 100. In the first month, 64 PM jobs fall due and 51 are done on time. Of the 13 missed, 9 were skipped because the machine was needed for an urgent order.

Month 1 (illustrative)CalculationResult
PM jobs dueFrom 38 tasks on 12 machines64
Done within the window51
PM compliance51 / 64 x 10079.7%
Missed because of a production clash9 of 13
One press hose failure, cost of the stop5.5 h x ₹9,000 lost output per hour + ₹6,000 hose, oil and clean-up₹55,500

What to do with it. The 9 clashes are a planning problem, not a maintenance one: move those PMs into the weekly planned stop and agree that slot with production. The hose failure shows why a 20-minute weekly hose and fitting check on each press earns its place. Track PM compliance and breakdown hours on the same 12 machines for three months before you widen the programme.

Common mistakes

  • Copying the whole OEM manual on day one. Two hundred tasks nobody can finish get ignored. Start with critical machines and the tasks that match their failures.
  • Setting every interval by the calendar. A press on three shifts wears faster than the same press on one. Use run hours, or whichever comes first.
  • Checklists that say "check machine". Each task needs what to check, the limit, and what to do when it is out.
  • Skipping PMs when production is busy. That is when machines work hardest. Agree the planned stop slot with production in advance.
  • Closing PMs without readings. A tick with no reading tells you nothing next month. Record the number, not just "OK".
  • Never reviewing intervals. If a PM keeps finding nothing, stretch it. If failures happen between PMs, shorten it or change the task.
  • Counting planned PM time as unplanned downtime in OEE. Planned stops come out of planned production time; only unplanned stops reduce availability.

Frequently asked questions

What is preventive maintenance in simple words?

It is planned work on a machine before it fails, such as cleaning, lubrication, inspection and part replacement, done on a schedule set by time, usage or condition.

What are the main types of preventive maintenance?

Time-based, usage-based, condition-based and predictive. Most plants use a mix, chosen machine by machine according to how each one wears.

How often should preventive maintenance be done?

Start from the OEM manual, then adjust with your own records. If a PM keeps finding nothing, stretch the interval. If failures happen between PMs, shorten it or change the task.

How do you measure preventive maintenance?

Track PM compliance: PMs done within their window divided by PMs due in the period. Read it alongside breakdown hours on the same machines, so you can see whether the PMs are the right ones.

Does every machine need preventive maintenance?

No. A cheap, non-critical item with a spare on the shelf can run to failure by choice. Put your PM effort on machines that stop the line, are hard to repair or have no standby.

What is the difference between preventive and predictive maintenance?

Preventive maintenance is planned on a time or usage interval. Predictive maintenance uses trends in condition readings, such as vibration or temperature, to decide when the work is needed.

Fix it before it fails.

Start a free trial today, or book a demo tailored to your plant, assets and standards.

Start with one line. Extend when it works.